  1. Concept
  2. Rezoning
  3. Engineering
  4. Permitting
  5. Plat recorded
  6. Under construction
  7. Selling
  8. Built-out

Environmental, stormwater, or building permits are under review.

Latest summary · Apr 15, 2026

As of public records through early 2026, Alford Farms is in engineering and environmental permitting — not selling homes. Putnam County approved an Agriculture-to-PUD rezoning on August 13, 2024 (Ordinance 2024-017, case PUD24-000004) for roughly 165 acres along SR 207 and Alford Road in East Palatka. The entitlement described up to 700 single-family homes plus about 60,000 square feet of commercial space, an amenity center, and a park. Later engineering materials (September 2025) show a 559-lot layout. D.R. Horton, Inc. is named as an agent in the county file; that is not the same as a published grand opening. St. Johns River Water Management District file 224892-1 was received August 29, 2024. An RAI went out February 20, 2025; a partial response followed in June 2025. No final plat recording or home-sale opening is confirmed in the records this tracker reviews. If a builder website lists the community, treat marketing as separate from county status.

Rezoning materials described up to 700 single-family homes. September 2025 engineering documents describe a 559-lot layout. The lower number is typical as plans move from entitlement to construction documents — it is not a cancellation.

Alford Farms. Open in OpenStreetMap

File facts

Numbers from the public file.

Area
East Palatka
Location
SR 207 / Alford Road, East Palatka
Acres
165
Lots (best known)
559
Lots at rezoning
700
Commercial sq ft
60,000
Builder / agent
D.R. Horton, Inc. (named as agent in county filings)
Applicant / developer
Charles Alford Jr. & Kathryn Clapp (applicants on rezoning)
County case
PUD24-000004
Ordinance
2024-017
SJRWMD file
224892-1

Timeline

  1. Jun 12, 2024

    Planning Commission recommendation

    Putnam County Planning Commission reviewed the Alford Farms PUD request and recommended approval 5–2.

    Source: Putnam County Planning Commission

  2. Jul 23, 2024

    BOCC first reading

    Board of County Commissioners advanced the rezoning on first reading, 4–1, with requested revisions.

    Source: Putnam County BOCC

  3. Aug 13, 2024

    PUD rezoning approved

    BOCC adopted Ordinance 2024-017, rezoning the tract from Agriculture (AG) to Planned Unit Development (PUD), case PUD24-000004.

    Source: Ordinance 2024-017

  4. Aug 29, 2024

    SJRWMD application received

    Environmental resource / stormwater application 224892-1 received by St. Johns River Water Management District.

    Source: SJRWMD file 224892-1

  5. Feb 20, 2025

    SJRWMD request for additional information

    District issued an RAI, which is routine on large residential ERP files and means the review stayed open.

    Source: SJRWMD

  6. Jun 15, 2025

    Partial RAI response

    Applicant materials were treated as a partial RAI response. Additional documentation was still required.

    Source: SJRWMD correspondence

  7. Sep 1, 2025

    559-lot engineering layout

    Engineering documents in the file describe a 559-lot development layout, down from the 700-home entitlement envelope.

    Source: County / permit engineering materials

  8. Mar 1, 2026

    Permit review still active

    Public reporting of the file in spring 2026 still showed environmental permitting as open. No confirmed start of home sales.

    Source: Public record compilation

Updates

  • Apr 15, 2026

    Alford Farms still in permit review, not sales

    Spring 2026 file reads still show SJRWMD and engineering work as the live step. Rezoning from August 2024 is the last major political milestone. No confirmed plat recording or model-home opening.